How much additional solid weight could be loaded at a VCG of 189.7 feet on the DEEP DRILLER while loaded as shown in the Sample Load Form #4 (Drilling)? Assume ballast added or discharged to maintain draft is done so at 15 feet above the baseline.

A
279.2 long tons
B
314.2 long tons
C
404.2 long tons
D
461.9 long tons