While on an ocean tow, the COASTAL DRILLER is threatened with the approach of a severe storm. Including the time required to place the generators on-line, the approximate time required to lower the legs from a TOC (tip-of-can) position of 12.38 feet to 60.5 feet is _____.

A
8 minutes
B
32 minutes
C
40 minutes
D
47 minutes