The DEEP DRILLER, loaded as shown in the Sample Load Form #4 (Drilling), discharges a non-liquid load of 275.8 long tons from a position 130 feet above the keel, 40 feet forward of amidships, and 30 feet to port of the centerline. What is the new GMT?
A
5.98 feet
B
6.84 feet
C
7.11 feet
D
9.24 feet
E
İlgili Sorular
Which condition would NOT indicate the approach of a tropical storm?All fire hoses on mobile offshore drilling units must be tested to a pressure of at least __________...The purpose of fuses in electric wiring is to ____________.BOTH INTERNATIONAL & INLAND Which is a distress signal?The internal volume of a cargo hold measured from the inside faces of the cargo battens, the lower s...