The DEEP DRILLER is on location during a storm. Windward anchor tensions begin to exceed the test tensions. To reduce tensions while minimizing offset over the well, you should ________________________.
A
increase tension on the leeward chain
B
pay out more chain on the windward side
C
reduce tension on the leeward chains
D
connect an emergency tow wire to the work boat
E
İlgili Sorular
Your vessel assumes an angle of loll of 6° after loading a deck cargo. The drafts are: FWD 16'-00", ...Electric cargo winches have an overload safety device which normally cuts the current to the winch m...On a vessel of 9,000 tons displacement there are two slack deep tanks of palm oil (SG .86). Each tan...You are on a large vessel fitted with a right-handed controllable-pitch propeller set at maximum for...What is the approximate geographic range of Race Rock Light, NY, if your height of eye is 27 feet (8...