The DEEP DRILLER is loaded as shown in the Sample Load Form #5 (Survival) when an unexpected slowly increasing port list and bow down trim occurs. A leak in C1P is found. By deballasting from ballast tanks 2P and 3P, the inclination slowly decreases. The increase in the transverse free surface correction is _________________.

A
1.25 feet
B
0.82 foot
C
0.34 foot
D
0.18 foot
E