The DEEP DRILLER is loaded as shown in the Sample Load Form #1 (Transit). Weather conditions make it necessary to ballast down to survival draft. It is decided to check the stability at the intermediate draft of 32 feet. How much ballast is required to ballast to 32 feet?
A
2,094 long tons
B
2,194 long tons
C
2,294 long tons
D
3,294 long tons
E
İlgili Sorular
BOTH INTERNATIONAL & INLAND A power-driven vessel is underway and fishing with trolling lines. This...To obtain better steering control when you are towing alongside, your vessel should be positioned wi...Marine Operators, when calling a ship on VHF-FM radiotelephone, normally call on channel ______.If there's a fire aboard your vessel, you should FIRST __________.Portable foam type fire extinguishers are most effective on _______.