The COASTAL DRILLER, when underway was loaded as shown in Sample Load Form #1 (Rig Move). It is now preloaded at minimum air gap waiting for all settling to take place. The preload, weighing 7,191.7 kips, has LM 870,196 ft-kips and TM 2,158 ft-kips. What is the bow leg reaction?
A
7,026 kips
B
7,099 kips
C
7,144 kips
D
7,180 kips
E
İlgili Sorular
What is the proper method to fix running rigging to a cleat?Fire fighting equipment requirements for a particular vessel may be found on the __________.The fitting that allows a boom to move freely both vertically and laterally is called the __________...Anyone voluntarily surrendering their license to a U.S. Coast Guard investigating officer signs a st...Roundline is a __________.