The COASTAL DRILLER is loaded as shown in the Sample Load Form #1 (Rig Move). If the entire contents of the port pipe rack are back-loaded to an offshore supply vessel, how much drill water would have to be transferred between tanks 6 and 7 to level the vessel in list?
A
47.2 kips tank #7 to tank #6
B
23.6 kips tank #7 to tank #6
C
23.6 kips tank #6 to tank #7
D
47.2 kips tank #6 to tank #7
E
İlgili Sorular
A vessel in ocean service that does not have an approved §means of processing oily bilge slops or oi...What is the lifesaving signal for "You are seen -§assistance will be given as soon as possible"?The DEEP DRILLER as currently configured is limited to a maximum drilling depth of _______________.Your vessel is taking on cargo oil when a small leak develops in the hose. You order the pumping st...The LMT of sunrise on the standard meridian is 0552. Your longitude is 99°15'E. What is your ZT of...