In anticipation of heavy weather, it is decided to deballast the DEEP DRILLER to survival draft. The marine riser should be disconnected, pulled, and laid down. After doing so, the riser tension will be ______________.
A
zero
B
equal to the weight of the riser
C
dependent on the water depth
D
applied at the riser tensioner sheaves
E
İlgili Sorular
The main function of a stripping system is to __________.The SS AMERICAN MARINER is ready to load the cargo listed. There is already 4184 tons of cargo on bo...The Certificate of Inspection of a damaged tank barge has expired. What certificate authorizes the ...The force acting on a single cargo runner which is vertically lifting or lowering a load is greatest...A magnesium fire is classified as class _______.