A semisubmersible with a displacement of 20,000 long tons and a KG of 52 feet discharges 300 long tons of barite from P-tanks located 120 feet above the keel. What is the change in KG?
A
0.79 foot downward
B
1.00 foot downward
C
1.04 feet downward
D
1.83 feet downward
E
İlgili Sorular
The order of importance in addressing damage control on a MODU is __________________.BOTH INTERNATIONAL & INLAND A vessel being towed astern, where the length of the tow exceeds 200 met...Where should the GMDSS radio log be kept on board ship?According to the regulations, normally, manholes in LFG tanks are located _________________________...According to the Chemical Data Guide, what is NOT a recommended extinguishing agent for an ethyl c...