Annual endorsment for load line certificate should be done;
A
3 months before and after the issue date
B
3 months before
C
3 months after
D
6 months before
E
6 months after
İlgili Sorular
Placing a lashing across a hook to prevent a fitting from slipping out of the hook is called You have been towing astern and have just let go the tow. Your deckhands are pulling in and faking t...... factories, which do not move, ships -when underway- are at risk from other ships, the weather co...Control the ship form the bridge.Which abbreviation refers to the horizontal distance measured between perpendiculars taken at the